| Executive
Summary The
Meander Dam is proposed to be constructed on the Meander River in Tasmania. It
is estimated to cost of $27 million and will hold 43,000 ML of water. It is intended
principally to provide water for irrigation, with the ability to supply 24,000
ML per year for this purpose. The
State’s Resource Management and Planning Appeal Tribunal overturned the construction
permit for the dam on environmental grounds. The Tasmanian Government has now
signalled the intention to introduce legislation that will allow construction
of the dam despite the ruling by the Tribunal. As
part COAG’s Water Reform Framework, States have agreed undertake certain obligations.
With reference to the proposed Meander Dam, the State’s obligation is to undertake
construction of the dam ‘…only when appraisal indicates it is economically viable
and ecologically sustainable’. In addition, States are obligated to price water
so that all costs are recovered. The
intention of this paper is to determine whether the proposed Meander Dam will
meet its COAG obligations. WWF Australia will focus on determining whether the
Project meets COAG’s economic requirements. This is not to diminish the importance
of the ecological impact of the project but rather to not duplicate the analysis
prepared by other organisations such as The Tasmanian Conservation Trust on the
environmental impacts of the dam.
Proponents for the construction of the Meander Dam have commissioned consultants
to prepare two documents providing the economic justification for the dam. Information
contained in these documents and the supporting surveys were used by WWF to assess
whether the proposed dam will meet the COAG economic commitments. On
the evidence provided, WWF concludes that the project is not commercially viable
and therefore will not meet COAG requirements specified in clause 3(d) (iii):
- The Net Present Value
of the project was assessed at between negative $16 million and $13 million.
If environmental costs were included this would be a larger loss.
- There is no justification
for the government subsidising construction of the dam based it providing public
benefits. Although some public benefits with a Net Present Value of $2 million
were identified by the consultants, no costs to the public (environmental, third
party) were included.
WWF
considers that full costs will not be recovered at the proposed price of $55/ML.
There does not appear to be scope for increasing the price, since any price above
this level has been demonstrated to reduce demand and total project revenue. Therefore
the project will not meet COAG obligations defined in clause 3(d)(i.). Introduction
The Tasmanian Department
of Primary Industries Water and Environment (DPIWE) is proposing construction
of a dam on the Meander River primarily for the extraction of irrigation water.
A Feasibility Study and a Draft Economic Evaluation have been prepared for the
dam’s proponents detailing the expected costs to be incurred and benefits to be
provided by the dam. The Council of Australian Governments (COAG) Water Reform
Framework specifies obligations agreed to by each state for construction of new
rural infrastructure and pricing of water. These form part of the National Competition
Policy (NCP). Conformance to this policy is assessed annually by the National
Competition Council (The Council). The
intention of this paper is to determine whether the Proposed Meander Dam will
meet its COAG obligations based on the information provided by the proponents. Background
The Meander Dam
is proposed to be constructed on the Meander River in Tasmania at the southern
end of the Meander Gorge at a cost of $27 million. It will contain 43,000 ML of
water, stand 48 metres high and 170 meters wide, and flood an area of 332 hectares.
It is intended principally to provide water for irrigation, with the ability to
supply 24,000 ML per year for this purpose. It also includes a mini hydroelectric
power plant with the capacity to provide 10,000 MWh of electricity per annum. The
dam has been designated a controlled action under the Commonwealth Environmental
Protection and Biodiversity Conservation Act 1999. Under the statutory process
of Tasmania’s Water Management Act and Environmental Management and Pollution
Control Act, a permit was issued in October 2002 for construction of the dam.
In January 2003, issue of the permit was overturned following an appeal to the
Resource Management and Planning Appeal Tribunal. The Tasmanian Government currently
plans to introduce legislation that will allow construction of the dam despite
the ruling by the Tribunal (Green (2003)). COAG
Obligations In
1994 the Council of Australian Governments agreed a Water Reform Framework. States
accepted an obligation to meet the requirements defined under the agreed Framework.
In relation to the Meander Dam proposal, these obligations relate to the construction
of new rural infrastructure, and pricing of water so that the all costs are recovered. States
have agreed under clause 3(d)(iii) of the COAG framework that in relation to rural
water supply (NCC (2001b)): ‘that
future investment in new schemes or extensions to existing schemes be undertaken
only after appraisal indicates it is economically viable and ecologically sustainable’ In
addition, clause 3(a) (i.) of the COAG framework specifies commitments in regard
to full cost recovery pricing being the: ‘..
adoption of pricing regimes based on the principles of consumption- based pricing,
full-cost recovery and desirability of the removal of cross subsidies.." This
report will focus on determining whether the Project demonstrates economic viability.
This is not to diminish the importance of the ecological impact of the project
but rather to not duplicate the analysis of other organisations such as The Tasmanian
Conservation Trust on the environmental impacts of the dam. The
Council considers that economic viability should be demonstrated in the project’s
ability to recover its direct costs and provide an adequate return to its investors.
New schemes should demonstrate the ability recover (NCC (2001a)):
- Administration,
operations and maintenance costs;
- Cost
of capital
- Externalities
(including environmental impact)
- Taxes
or tax equivalent regimes; and
- Provision
for asset consumption
Externalities
were defined by the Council to include environmental and resource management costs
attributable to and incurred by the water business. The Experts Group (COAG (1995))
has further defined environmental costs as: a.
River Management costs including:
- Costs of implementing resource
management initiatives. -
On-going costs associated
with resource management and monitoring. b. The
allocation of natural flows to meet environmental requirements. Broader
costs and benefits to society also need to be considered on larger projects, such
as dams. Costs include for example, broader environmental impacts and downstream
effects, while benefits could include the impact of increased economic activity.
The
Council suggests that governments should only consider providing assistance for
construction of new water storages ‘… once the stand alone viability of the project
has been demonstrated’ (NCC (2001a)) Economic
Assessment-Meander Dam Proponents
for the construction of the Meander Dam have commissioned consultants to prepare
two documents providing the economic justification for the dam:
-
Meander
Dam Feasibility Study-Agricultural & Economic Report March 2002 ( Feasibility
Study) Davey &
Maynard Agricultural Consulting, Deloitte Touche Tohmatsu, and
Serve-Ag Pty Ltd -
Meander
Dam Proposal-Draft Economic Evaluation December 2002 (Economic Evaluation)
Davey & Maynard
Agricultural Consulting These
reports are supported by two surveys of approximately 100 farmers interested in
receiving additional water intended to determine the potential demand. The first
survey was conducted in September 2001. It identified demand for an additional
24,700 ML of water, 11,300 ML by irrigators with Meander River frontage. Prospective
users were re-surveyed in February 2002. This survey included consideration of
the price to be charged for water. At a price of $55/ML demand for water was 22,000
ML, with 15,500 on the Meander River. Demand was greatly reduced at higher prices. Information
contained in these documents and the supporting surveys were used by WWF Australia
(WWF) to assess whether the proposed dam will meet the COAG economic commitments. Feasibility
Study- March 2002 In
March 2002 a feasibility study was prepared for the Meander Dam. The analysis
provided in the Feasibility Study did not indicate conclusively whether or not
the project was financially viable, that is whether it is capable of providing
an adequate return to investors. Sensitivity analysis was run for various scenarios,
but judgement is not made as to the most-likely situation, nor is the detailed
financial analysis provided. Statements
made in the Study are vague and contradictory, but in general indicate that the
project is not financially viable: - "…there
are good prospects for scheme proving to be financially viable" (p.1);
- "To
be financially viable at the anticipated capital cost, Government contribution
may need to be provided at no return." (p.1),
- "At
this cost a commercial viewpoint of the project on a stand-alone basis indicates
that it requires additional assistance…"(P.1);
- "The
level of capital required for the project of $29.397M provides a low return on
investment under a range of demand scenarios" (p.45)
Based
on information provided in the study document WWF prepared a most-likely case
scenario for the project. Details of the assumptions underlying this scenario
are shown in exhibit 1a. The key assumptions underpinning the projects value are
the likely volume of water to be demanded by irrigators and the price that can
be charged for that water. Volume
assumption: The
estimated likely demand for irrigation water was based on the results of water
demand surveys conducted in September 2001 and later in February 2002. The latest
survey included price considerations and concluded that demand for additional
water was as follows: (p.16) Meander
river frontage 15,500 ML @ $55/ML price
10,600 ML @ $75/ML price
5,225 ML @ $110/ML price Off-river
demand 6,585 ML @ $55/ML price
960 ML @ $75/ML price
530 ML @ $110/ML price Report
considered off-river demand "unlikely to be realised" due to delivery
costs of close to $100 ML (p.14). In addition it was estimated that there would
be a 25% loss factor, as water was transferred to these secondary streams (P.31).
The
effective cost to off-river users would then be:
Water Cost $55 ML
Transfer Loss $14 ML
Delivery $100 ML
$169 ML At
this price there is likely to be negligible demand by off-river users. It is therefore
concluded that a reasonable estimate of water demand would be only that of those
users with river frontage: 15,500ML/yr at a price of $55. Consistent
with timing assumptions included in the analysis (p.40), it was assumed that volumes
would reach a level of 15,500 ML/year by year 7, with 20% of the demand taken
up in year 3, 40% in year 4, 60% in year 5, 80% in year 6. Price
Assumption: The
February survey showed the incremental demand water for by Meander irrigators
with river access at various price levels. The revenue produced at each price
is shown as follows: Price
ML Volume ML Revenue ($000)
$55 15,500 $852.5
$75 10,600 $795.0
$110 5,225 $574.8 
$55/
ML was selected as a reasonable price for water given that it produces highest
level of revenue. Increases in price above this level will reduce the value of
the project. The information can be shown graphically as follows: Based
on the Discounted Cash Flow analysis presented in exhibit 1b, WWF concludes that
under the most-likely case the project will return a negative $16M to those
entities funding the dam: Project
Net Present Value ($millions)
Irrigation
-$16.8 Hydro
0.7 Total
-$16.0 Economic
Evaluation December 2002 In
December 2002, a revised economic analysis of the Meander Dam was prepared by
consultants Davey & Maynard. This analysis attempted to incorporate the broader
impacts of the dam but also altered some of the fundamental underlying assumptions
of the project. A major change was that the forecast demand for water was increased
significantly and timing of that demand was moved forward, with no detail provided
on water pricing. Details of these assumptions are as follows: Volume
Assumption: The
analysis assumes the initial demand of 15,500 ML/year will be reached over the
four year period after completion of the dam. From that point the demand for water
is assumed to continue to increase reaching a level of 24,000 ML/year within ten
years. The maximum demand level of 15,500 ML/year estimated in the feasibility
study was based on the two surveys conducted and consideration of the price to
be charged for water. It is difficult to conceive of a rationale that would change
this key assumption and indeed the Economic Analysis has provided none. Will the
price of water be reduced? Will more land than anticipated be brought into production?
Will off-river users elect to pay $169/ML for water? Will irrigators be asked
to pay for all water used rather than only the additional demand? 
The
following illustrates the difference between the two volume assumptions : Price
Assumption: The
Economic Evaluation did not explicitly forecast the price of water. It was assumed
that the cost of water to irrigators is $55/Ml. This price has been assumed to
apply to the total level of water demanded. However it may not be appropriate
to apply this price to volumes in excess of 15,500 ML/year, since the Survey showed
this as being the maximum level demanded at that price. A significant reduction
in the price would be required to boost demand 55% as forecast. The lower price
would reduce the Project’s value. Based
on the information provided in the Economic Evaluation, WWF prepared a Discounted
Cash Flow analysis (exhibit 2b) to determine the projects financial viability.
Despite the more optimistic assumptions shown in exhibit 2a, the value of the
project for those funding the dam remains negative: Project
Net Present Value ($ Million)
Irrigation
-$12.3 Hydro
2.1 Total
-$ 10.2 If
the assumption on the maximum volume demanded is reduced to 15,500ML/yr,the level
supported by the survey information, the resulting Net Present Value of the project
will decline to negative $13M: Project
Net Present Value ($ Million)
Irrigation
-$15.4 Hydro
2.1 Total
-$ 13.3
Does
the Proposed Meander Dam meet COAG requirements? It
is clear, from the information provided on the project, that it will be unable
to meet its direct costs and provide a return to investors. The analysis presented
above has indicated in the most-likely case, the project will produce a negative
Net Present Value of between $13 and $16 Million. Even if the water demand were
assumed to increase to the dam’s maximum capacity, and pricing remained unchanged,
a loss of $10 million would be realised in present value terms. There is a significant
risk that even these returns are over-stated. Assumptions on the volume of water
demanded are very optimistic. It is assumed that the maximum level of water demanded
is available and used each year. Given the variability of stream flows, this is
unlikely. Reduced volume assumptions would further undermine the value of the
project. The
Council has included both externalities (environmental costs) and taxes as direct
costs that should be recovered in investment in new infrastructure. These costs
have not been included in the analysis and their inclusion will have a further
negative impact on the project. The
consultants’ report has identified direct environmental costs due to changed geomorphology,
impacts on threatened plants and impacts on threatened animals but mitigation
costs have not been estimated or included in the analysis. TCT has identified
loss of habitat for the Spotted Tail Quoll (Dasyurus maculatus) and environmental
harm to the rare plant species Epacris (Epacris aff. Exserta) as
key environmental impacts. Revenue from the Dam is required to cover these specific
mitigation costs and broader resource management costs. Inclusion of these costs
is likely to significantly reduce the value of the Project. The
council has also indicated the taxes or tax equivalents should be included in
project costs. Commercial investor’s gains on the project would clearly be subject
to taxation. It can also be argued that the Government’s returns should be subjected
to a Tax Equivalent Regime in the interests of Competitive Neutrality. It
is clear that revenue generated by the proposed Meander dam will be insufficient
to cover direct costs and provide a return to investors, it is therefore considered
not to have meet COAG’s obligation to achieve economic viability as defined in
clause 3(d) (iii). In addition, full cost recovery will not be achieved at the
proposed price of $55/ML and price increases above this level will reduce demand
and total revenue, therefore the project will not meet the obligations in clause
3(d)(i.) Broader
economic considerations The
question arises as to whether the Government should subsidise the dam, despite
its not being financially viable, to achieve public benefits. The Economic Evaluation
has made an attempt to quantify both benefits to the general public and those
benefits accruing directly to irrigators. The
consultants have made a significant effort to quantify the benefits to the community
in terms of flood mitigation, water quality and recreation. These have been valued
at an NPV of $2.2 million. Unfortunately the costs to the community particularly
the environmental impact due to construction of the Dam, increased irrigation,
disruption of flows and sedimentation, have not been quantified. The
report also shows that the dam will provide a significant benefit to individual
irrigators. However, the analysis excluded any consideration of the price irrigators
would be required to pay for water. Use of 24,000 ML a year was assumed, but the
survey indicated that a maximum of 15,500 ML would be demanded at a price of $55/ML.
At higher prices, the volume of water demanded by irrigators drops precipitously.
The assumption that additional water will provide a significant benefit to irrigators
is not supported by the willingness or irrigators to Pay for additional water
as indicated by the survey. Based
on the information provided, WWF concludes that economic analysis is incomplete,
since no costs to the community have been included and benefits to irrigators
are not supported by survey data. In addition there are issues on the distribution
of costs and benefits, with the majority of benefits accruing to irrigators, while
cost are absorbed by the general community. As a consequence, WWF considers that
there is no justification for the Government
subsidising the construction of the Meander Dam based on it providing public benefits. Other
issues - A
part of the rationale used to justify the dam is that it provides an economic
benefit by providing environmental flows. Actually this is not the case, what
the dam does is make additional water available to irrigators who have been required
to reduce extractions to provide environmental flows. The dam provides a benefit
to the irrigators. Environmental flows would be required in either case.
- It is not clear what the
relationship (if any) is between the level of water extracted for irrigation and
that available to drive the hydro plant. It seems that the more water extracted
above the dam, the less available to drive the turbine. No relationship is postulated
in the analysis.
- The
WWF analysis has relied on the assumptions and data provided by the consultants.
However there remain issues which are open to debate, for example: the appropriate
cost of capital to apply; inclusion of dam decommissioning costs, as recommended
by the World Commission on Dams (WCD (2000)); the validity of the surveys used
to determine Willingness to Pay; other options for supply of irrigation water
and hydro power; equity and distribution of costs and benefits. Should the dam
proceed, the validity of these and other assumptions may need to be explored.
Conclusion
WWF has reviewed
the information provided by the consultants engaged by the proponents to provide
the economic justification for construction of the Meander Dam. The intention
was to determine whether the project would meet the Tasmanian Government’s obligations
under COAG’s Water Reform Framework. The report focuses on COAG’s requirement
that new rural water supply infrastructures are economically viable and that water
is priced to achieve the full recovery of costs. On
the evidence provided, WWF concludes that the project is not economically viable
and therefore will not meet COAG requirements specified in clause 3(d) (iii):
- The Net Present Value
of the project was assessed at between a negative $16 million and $13 million.
If environmental costs were included this would be a larger loss.
- There is no justification
for the government subsidising construction of the dam based it providing public
benefits. Although some public benefits, with a Net Present Value of $2 million,
were quantified by the consultants, no costs (environmental, third party) were
included.
WWF
considers that full costs will not be recovered at the proposed price of $55/ML.
There is no scope for increasing the price, since any price above this level has
been demonstrated to reduce demand and total project revenue. Therefore the project
will not meet COAG obligations defined in clause 3(d)(i.).
References
Council of Australian
Governments (COAG) (1995) Report of the Experts Group on Asset Valuation Methods
and Cost Recovery Definitions for the Australian Industry 2/95 Davey
& Maynard, Deloitte Touche Tohmatsu, Serve-Ag (2002) Meander Dam Feasibility
Study-Agricultural and Economic Report Prepared for Department of Primary
Industries Water and Environment Davey
& Maynard (2002) Meander Dam Proposal-Draft Economic Evaluation Prepared
for Department of Primary Industries Water and Environment Green
G (2003) Meander Dam Proposal to go to Parliament www.media.tas.gov.au NCC
(National Competition Council) (2003) The 2003 National Competition Policy
Assessment Framework for Water Reform Ausinfo, Canberra. NCC
(2001a) Background Paper- Rural Water Pricing Ausinfo, Canberra. NCC
(2001b) Background Paper- New Investment in Rural Water Infrastructure
Ausinfo, Canberra. WCD
(World Commission on Dams) (2000) Dams and Development: A new framework for
Decision Making http:// www.dams.org |