Contents
List
of attachments
Attachment 1:
Bushcare costing
of land rehabilitation
Attachment
2:
Comments by Manager of Resource Management and Conservation Division,
DPIWE, on Meander Dam Supplementary DPEMP
Attachment
3:
Comments from Resource Management and Conservation Division, DPIWE, on
Meander Dam DPEMP
Attachment
4:
Comments by Nature conservation Branch Botanist on Meander Dam DPEMP
Attachment
5:
Original Nature Conservation Branch Epacris aff. exserta
(Union Bridge) Impact Statement
1.
Impacts of the proposal on Epacris aff. exserta (Union Bridge)
Epacris aff. exserta (Union Bridge) is
listed as Vulnerable on the Threatened Species Protection Act 1995 and
as Endangered on the Environment Protection and Biodiversity Conservation Act
1999. There are only 21 known populations of this species, totalling just
over 7,100 individuals at best. Approximately half of all known individuals are
found on the Meander River, including the largest known colony (designated Eub5
and comprising of 1,811 individuals) just downstream of the proposed dam site.
There
are two major risks that have been identified to the Epacris aff. exserta
populations on the Meander River if the Meander Dam were to be built. These are:
"1.
Erosion of habitat due to increased scour in a sediment starved environment in
which the river may source new sediment from the habitat.
2.
Erosion of habitat due to increased susceptibility resulting from inundation and
consequent waterlogging and loss of riparian vegetation."
(Population
structure and habitat of Epacris aff. exserta (Union Bridge) on the Meander River,
North, Barker and Associates, page iii).
It
is also worth noting the following information from the Meander Dam DPEMP Supplementary
Information in relation to floods:
"During
wet winters, only the first few high flow events are captured behind the (largely
full) dam, with the frequency and magnitude of winter high flow events identical
to the natural hydrograph. The only difference the dam appears to have in wet
winters periods is to result in higher base flows (5.5 m3/s) between high flow
events." (page 38).
Theses
two pieces of information present a seemingly irreconcilable conflict for the
management of impacts on Epacris aff. exserta. In wetter years, the higher
base flows between high flow events will result in inundation and waterlogging,
whilst the frequency and magnitude of flood events will hardly be altered from
normal. Releases from the dam for irrigation purposes over summer may also contribute
to this waterlogging. It is also worth noting the following statement from the
Meander Dam DPEMP Supplementary Information:
"Since
the finalisation of the Geomorphology assessment (Locher et al, 2002), the projected
hydrology of the proposed dam has changed significantly, due to a change in the
size of the turbine associated with the mini-hydro development." (page 38)
As
a result of this, the flow regimes have been revised, but the assessment of geomorphological
impacts, and hence impacts on the Epacris aff. exserta, have not been revised.
It is astonishing that such a significant change in the operation of this proposal
did not result in a revising of impacts on a threatened species.
The
largest known population of this species (approximately 1811 individuals, as above)
is found at and immediately downstream of the proposed dam site. A small number
of individuals (approximately 118 - Environmental Assessment Report, page 63)
would be destroyed by inundation of the dam sites, with the remainder of the population
to be impacted upon as described below:
"Eighty
percent of these plants are on habitat that the fluvio-geomorphic assessments
suggest may be lost to erosion over an unknown but extended period (possibly 100-300
years). Assuming the loss of approximately 1448 plants this would represent a
decline of about 20% over that period."
(Extension
Survey and Conservation Assessment of Epacris aff. exserta, North, Barker
and Associates, page 8)
This
report also goes on to state that:
"The
population is important because it is the largest and thus is buffered against
stochastic loss due to fluctuations in numbers. It is also likely to be a source
of seed for the maintenance of the downstream populations." (page 9)
With
regards to the populations present on the Mersey River, the document Geomorphic
response of the Mersey River and population response of Epacris aff. exserta (Union
Bridge) to flow regulation by North, Barker and Associates draws the following
conclusions (page 38):
-
The
loss of the alluvial sediment supply due to dams is allied to future habitat loss
as the sediment supply moves through the system over an extended but unknown period,
possibly several centuries. The sediment supply from tributaries below Union Bridge
may be sufficient to sustain some of the new Flood Plain Deposits.
This
indicates that the Mersey River populations of Epacris aff. exserta
(Union Bridge) are also expected to decline in the medium to long term because
of impacts of river regulation.
The
proponent’s response to these issues is contained within three documents
- Meander Dam Downstream
Flora Management Plan
- Management
Plan for Epacris aff. exserta (Union Bridge) in the Meander and
Mersey Rivers and Lobster Rivulet
Pre-construction
and construction commitments aside, the first of these documents outlines monitoring
and reporting protocols. This is not mitigation. The second of these documents
also deals with monitoring and reporting, as well as committing to some weed control,
fencing, signage and ex-situ propagation. The latter commitment appears to be
highly problematic, as this ex-situ population could not be used to establish
a new population along the Meander River, as it is stated that:
"The
available suitable habitats within the Meander River have Epacris on them now.
Additional habitat that may be chosen for ex-situ planting is therefore likely
to be marginal and immediately at risk of failure."
(Population
structure and habitat of Epacris aff. exserta (Union Bridge) on the Meander River,
North, Barker and Associates, page 30).
Additionally,
this ex-situ population could conceivably be used to re-establish a population
that was lost due to the operation of the dam. However, as the proposed mitigation
measures do not directly address those aspects of dam operation that might impact
upon Epacris aff. exserta (Union Bridge), any population that is
re-established at a site where a population has been lost due to the operation
of the dam could be reasonably expected to be lost as well.
The
third document deals with management of populations of this species within State
Forest. Not only does this document not commit to anything that a resource management
agency could be reasonably expected to undertake anyway, it also does not address
the principle issues facing this species.
In
summary, even if all commitments are fully met and implemented, if the proposed
Meander Dam proceeds then there will be an irreversible decline of all populations
of Epacris aff. exserta (Union Bridge) on both the Mersey and Meander
Rivers. In the long term, only the population on the Lobster Rivulet (less than
10% of the current population) will not be subject to decline, but will, like
the degraded populations remaining on the Mersey and Meander Rivers, be susceptible
to catastrophic events. It is completely plausible that the construction and operation
of the Meander Dam will, in conjunction with a number of other factors, result
in the extinction of Epacris aff. exserta (Union Bridge). Further,
the acknowledged loss of the majority (80%) of the largest known population of
this species (Eub5) as a direct result of the proposed Meander Dam is a significant
impact within the terms of the guidelines for assessment under the` Environment
Protection and Biodiversity Conservation Act 1999. On the other hand, should
the dam not proceed, there is every chance of securing the Meander River populations
of this species.
2.
Impacts on the proposal on spotted-tailed quoll Dasyuris maculatus
The spotted-tailed quoll has been recommended to be
listed as Vulnerable on the Threatened Species Protection Act 1995 and
is listed as Vulnerable on the Environment Protection and Biodiversity Conservation
Act 1999. The TCT is very concerned about the document entitled Meander
Dam Mitigation Strategy for the Spotted-tailed Quoll (Dasyuris maculatus). The
primary focus of this document, and of the proponent’s mitigation measures, is
the provision of compensatory habitat. We would like to draw your attention to
the following statement:
"
‘Compensatory habitat’ is a term used where habitats are constructed artificially
(often wetland areas) in an attempt to compensate for an area of natural habitat
that is going to be destroyed. Modern practice in natural heritage conservation
does not support this approach - it is regarded as a last resort. The complexity
of natural habitat and the interactions of the components cannot be replicated
artificially (although very simple systems can be created, such as planting reeds).
This is not the same as retaining the original ecosystem, with all of its component
species, ecosystems and earth processes."
(Protecting
Natural Heritage - using the Natural Heritage Charter, Commonwealth of Australia,
2003, page 124)
Applying
this principle, the proposed mitigation measure of rehabilitating 140 ha of cleared
pasture for new habitat is unacceptable, as well as quite possibly unachievable.
The time that would be taken for this habitat to become useful must also be questioned,
as spotted-tailed quolls have short life spans.
We
are also concerned about the structure of the proposed ‘Special Management Zone’
(SMZ). This area is extremely narrow and bordered on most sides by either couped
State Forest or hardwood plantation. The purpose of the SMZ appears to be exclusively
as a wildlife corridor, and ignores the obvious value of the proposed inundation
site to this. Intensive trapping revealed that there are very few populations
of this species remaining in the area that is bound by the Great Western Tiers
and the Bass Highway from Mole Creek to Jackeys Marsh (H. Hesterman, personal
communication). Correspondence and communication with a number of experts has
led us to believe that it is very likely that this unusually dense population
is a source population for the region, and/or the proposed inundation area serves
as refugia for this species. Quite obviously, this emphasises the importance of
the proposed inundation area to the species as a whole. In light of this, mitigation
measures designed mostly to address the issue of a maintaining a wildlife corridor,
equating to a simple passage through the area, will not be adequate.
The
proximity of couped State Forest and hardwood plantations to the proposed ‘Special
Management Zone’ also presents a number of other significant problems. It is worth
noting that no provisions for the restriction of 1080 poisoning have been undertaken,
despite there being some considerable concern at the incidence of secondary poisoning
of this species.
The
presence of abundant prey must obviously be a key factor in the density of spotted-tailed
quoll at the site of the proposed dam. However, the mitigation measures do not
address this issue, and there would appear to be no guarantee that prey would
be present in the same abundance post-inundation. Thus, even if compensatory habitat
was successfully provided, without abundant prey it would be completely useless.
The same concerns that have been expressed about the impacts of forestry activities
and 1080 poison on quolls are doubly true for their prey species, as such animals
are the primary targets of 1080 poison and must be present in large ratios to
resident quolls.
In
summary, the proposal to rehabilitate improved pasture to make top-quality quoll
habitat is fanciful and is unlikely to be achieved at all, let alone in sufficient
time to be of any use. Reservation of couped State Forest could only be deemed
successful if reservation was long term and other forestry activities were controlled,
but in any case would replace an area of very high quality habitat with a very
low edge:area ratio with a lesser area of lower quality habitat with a very high
edge:area ratio.
3.
Other ecological impacts of the proposal
As
well as impacts on the two threatened species discussed above, there are a number
of other ecological impacts which contribute to the dam’s failure to be ecologically
sustainable.
Other
native fauna
This area supports a dense fauna assemblage,
including Eastern barred bandicoots Parameles gunnii gunnii, Eastern quolls
Dasyuris viverinnus, Tasmanian devil Sarcophilus laniarius, Tasmanian
pademelon Thylogale billardierii and brushtail possum Trichosurus vulpecula.
The presence of the masked owl Tyto novaehollandiae was never confirmed,
despite evidence that this species was present: "Considering
the available habitat, it is also likely that the area provides excellent habitat
for owls. This was strongly supported by the discovery of the remains of an adult
ring-tailed possum and a ‘young at foot’ pademelon, both decapitated, found under
perches on large old trees. This feeding style is typical of owls (B. Brown, TPWS,
pers. comm.)."
(DPEMP,
page 124)
As
there are only two owl species in Tasmania, the larger of which is the masked
owl, it is quite reasonable to assume that this is the species that is present.
No further assessment has been made of the presence of this species. This would
seem to be a serious omission, as there are generally considered to be less than
1,500 breeding adults remaining in Tasmania, where it has a status of Endangered
on the Threatened Species Protection Act 1995. As it is widely recognised
as a subspecies, it would also qualify as endangered on the Environment Protection
and Biodiversity Conservation Act 1999. It must also be questioned whether
or not a permit has been issued in relation to possible impacts on this species.
Native vegetation
Inundation will result in the loss of 50.5 ha of intact
native forest and over 200 ha of regenerating forest. In response to this, the
proponent has offered to set aside 243 ha of couped forestry land, which may or
may not be cleared in the future, as well as attempt to regenerate 137 ha of native
vegetation from improved pasture. In other words, there is no guarantee that the
250 ha of native vegetation that would be lost due to inundation will be replaced.
Further,
an examination of the report Landscape Change in the Meander Valley: A
Case Study for Monitoring and Reporting of Land Use Modification, Vegetation Condition
and Biodiversity Loss (Cadman, Bushcare Tasmania, 2003) shows that there are
major losses of native vegetation occurring in this region.
"In
the period 1995 – 2000 2993 ha of native woody vegetation was lost to plantations,
agricultural development or urbanisation in the Meander Valley." (page i)
"Four
sub-catchments within the overall landscape are at or below the critical thresholds
of woody vegetation and by inference native vegetation cover of 30%…A further
4 sub-catchments are at significant risk of reaching this threshold and the trend
of clearance over the time sequence of the study for [two additional sub-catchments]
are cause for some concern." (page 13)
Riparian and riverine
ecology
The
following table is taken from Downstream Meander Dam Fluvial Geomorphology
Assessment (Locher et al, Supplementary DPEMP, May 2003, page 6) and characterises
physical responses of rivers to regulation.
Category
of change Type of response
| Flow |
Reduction
in magnitude of mean annual flood Altered flow frequency distribution
Flows less variable Less frequent bankfull and overbank discharges |
| Sediment
Load | Bed load sediments trapped in reservoir
Suspended sediments settle out in reservoir Tributary rejuvenation can
increase tributary sediment contribution to stream |
| Channel
Morphology | Degradation and/or aggradation
Channel width may increase or decrease Armouring of channel bed
Lateral migration of bends |
The
impacts of these physical changes are explained in Population structure and
habitat of Epacris aff. exserta (Union Bridge) on the Meander River (North,
Barker and Associates, Supplementary DPEMP, April 2002, page 7):
"Hupp
(1985) described the relationship between the rivers energy and the development
of depositional landforms that are typically indicated by different vegetation
types; that is they provide different habitats. It follows that the variation
in the hydromorphic processes operating along the course of a river contributes
to the distribution of a plant species along the banks of a river. When the habitats
of plants (river banks) are disturbed by flood the form of the bank can recover
as it is redeposited and becomes revegetated. This dynamic process is an important
feature of the geomorphic/vegetation relationship on river banks (Hupp and
Simon
1991). However, in regulated rivers the sediment supply is interrupted and so
to is the potential for natural habitat dynamics to continue. In the sediment
starved system the potential for habitat erosion without redeposition by a stream
with increased energy arises as a threat. It is the management of the streams
energy that may provide the answers to ameliorating the impacts in some instances.
A
second key area of concern with regard to riparian vegetation is the impact of
inundation. Many species are adapted to extended periods of inundation (Blom et
al. 1990) and indeed some are aquatic. But in terms of the persistence of
the existing riparian vegetation there will be some species that are fragile and
some that are resilient to increased inundation (Nilsson et al. 1997).
So in the absence of habitat destruction there may be a change in the species
composition in response to inundation and this will depend upon the length of
the period of inundation (Hughes 1997, Ladiges & Foord 1981) and importantly
the rate at which change is implemented. If the period of inundation is dramatically
different to the natural one all species may be killed."
While
this section of the Meander River has little aquatic vertebrate fauna, the Meander
Dam DPEMP states the following with regards to invertebrate fauna:
"A
total of 48 taxa were identified from the composite kick samples and AusRivAS
samples (Table 7.5). This collection of animals was composed largely of stoneflies
(Plecoptera), mayflies (Ephemeroptera), caddisflies (Trichoptera), aquatic beetles
(Coleoptera) and aquatic larvae of flies (Diptera), which is broadly characteristic
of a fast-flowing habitat dominated by cobble and boulder sized substrate. Many
of the taxa identified are characteristically found in rivers where water quality
is good and there is minimal impact to instream aquatic habitat." (page 130)
This
assemblage of species will quite obviously not persist in the impoundment area
should the dam proceed, and is unlikely to persist intact downstream of the proposed
dam. In short, there will be significant impacts on aquatic invertebrates in the
vicinity of the proposed dam.
In
summary:
-
The
riparian zone and aquatic habitat of the Meander River downstream of the dam would
suffer irreparable change;
-
The
riparian zone and aquatic habitat of the Meander River within the impoundment
area of the dam would suffer irreparable change;
-
Over
250 ha of native vegetation will be destroyed, with no guarantee of effective
replacement or reservation of other areas;
-
Numerous
native fauna species will be displaced or destroyed.
In
the few cases where the proponent has offered mitigation measures for these impacts,
it consists almost entirely of monitoring and reporting. This is not mitigation.
4.
Economic viability of the proposal
Before dealing
with the broader economic issues, the veracity of the fundamental information
on which the economic viability of this proposal is based must be examined. The
original mail survey, on which the justification for the entire project is based,
was conducted in September 2001. Since this time, on-farm dams with a total capacity
of around 2,000 ML have been formally applied for in the Meander Valley. Most
have been approved. Amongst these applications is the family business of one of
the main supporters of the dam. Also in this period, local milk buyer TQM collapsed
and poppy company Tasmanian Alkaloids announced a significant cutback in production.
Using data that is almost two years old, and not based on any firm commitment
to purchase water or realistic price discussion, calls into serious question the
accuracy of the information upon which economic forecasts have been based.
It
is worth noting at the outset that Marsden Jacob Associates (MJA) did not meet
with the TCT or any other group or individuals opposed to the dam, and thus were
offered a very one-sided view of this proposal whilst compiling their economic
appraisal. This would seem to be at odds with the recommendations of the National
Competition Council, as articulated in the document New investment in rural
water infrastructure:
"Assessments
of economic viability should involve an open transparent process. In its draft
report on the "Impact of Competition Policy on Rural and Regional Australia",
the Productivity Commission recommended that all cost benefit cost studies should
be publicly available. To this the Council adds that studies should involve an
appropriate amount of consultation with relevant stakeholders." (page 4)
Despite
not being formally consulted as could be expected, the TCT agrees with a significant
number of the assumptions and calculations that MJA have used, as they are much
more realistic than those presented previously. In summary, we believe the faults
in the MJA analysis fall into two broad groups, which we will address below.
(a)
Inaccuracies in assumptions
Willingness
to pay
It
is difficult to accept that irrigators would only be prepared to pay $55 per ML
when the benefits are up to 5 times this much to their business.
Risk
MJA states that "Arguably, a highly reliable dam servicing
an established and diversified customer base of dairying and high-value cropping
might be regarded as less than average risk and therefore command a lower discount
rate." (page 13). This statement is in direct contradiction with the Commonwealth
Competitive Neutrality Complaints Office, which assigns dams a medium risk factor.
Environmental
flows
MJA state "Moreover, we have assumed that introduction of environmental
flow policy would be implemented within two to three years." (page 21), going
on to cite the Water for Ecosystems Policy under the Water Management Act 1999.
What is ignored is the provision within this policy for the Minister to approve
a high risk Water Provision for the Environment flow (for example, approximate
to the status quo). Further, MJA also ignore the only documented case of an approved
Water Management plan (Great Forester) in Tasmania, where a Water Provision for
the Environment flow only 5ML/day higher than the current flow was approved for
a period of three years.
In
short, even an assumption of a phase in of environmental flows by 2010 is very
optimistic under current conditions in Tasmania.
Environmental
mitigation
The environmental mitigation costings supplied to MJA are flawed,
which is little surprise considering their source. For example, the one-off allocation
of $10,000 for quoll mitigation is only a fraction of what is necessary, and the
allocation of only $200,000 for the rehabilitation of land works out at less than
$1,500/ha. As far as the latter point is concerned, the proponent was advised
that normal costs for such rehabilitation are in the order of $3,500/ha with an
additional $3,500/ha to maintain for additional 10-15 years (see Attachment #1).
At this rate, $959,000 would be necessary for the rehabilitation of this area.
Further,
it is proposed that 243 ha of couped State Forest be placed into a Special Management
Zone for quolls, subject to review. At worst, this public asset might be completely
removed from production, which is an economic cost. One hectare of forest would
be expected to yield between $5,000 and $10,000 in royalties, and so if the full
area were to be removed from production the economic cost would be between $1.2
and $2.4 million.
(b)
Optimistic construction of scenarios
The
TCT agrees with many of MJA’s assumptions and calculations, but disagrees with
the optimistic manner in which these factors have been structured into a cost
benefit analysis. We would therefore like to present this alternative analysis
for consideration.
Project
Component NPV @ 6% ($ Millions)
Recovery
of Environmental Flow Restrictions 8.8 1
Additional
Irrigation
-Adjacent
to River 21.1 2
-Away
from River 0.0 3
Electricity
Generation 2.0 4
Other
Benefits 1.1 5
System
Costs - 31.5 6
Environmental
Mitigation - 2.0 7
Recovery
of assessment costs - 0.75 8
Net
Present Value - 1.25
Project
IRR 5.7 %
This
economic scenario does not comply with National Competition Policy guidelines.
The application of a higher discount rate, between 7 and 10.5%, for example, in
line with that recommended by NCC, CCNCO and NSW Treasury, would reduce the NPV
and the IRR further, or alternatively, would compensate for some ‘improvement’
in one of the other assumptions.
5.
Financial viability of the proposal
The National
Competition Council states the following with regards to financial viability:
"The
Council suggests that government assistance should not be included in considering
whether or not a project can recover its direct or broader costs. The CoAG Framework
does not preclude governments from transparently subsidising the prices charged
by water service providers. However, it is the Council’s view that if governments
wish to subsidise prices upon completion of a new investment this should be considered
separately
from calculations of commercial viability. Under this approach governments therefore
face two separate questions when considering future rural investment projects:
1.
Is the project able to recover all costs on a stand alone basis?
2.
What price should service users be charged upon the projects completion?"
(New
investment in rural water infrastructure NCC, page 4)
There
would appear to be no question that this proposal is not financially viable on
a stand alone basis. This has been established and acknowledged numerous times.
How this complies with National Competition Policy is not as clear. It is, however,
the TCT’s view that seeing as how the proponent asserts that this proposal is
economically robust, the question must be asked why provide a substantial taxpayer
funded grant to overcome commercial issues? We would argue that the provision
of one third of the total budget of an allegedly commercial enterprise in the
form of a taxpayer funded grant is at the very least against the principle, if
not the letter, of NCP.
It
is also worth noting the apparent problems that would be encountered trying to
overcome basic financing options:
"Discussions
with the 26 owners identified 14 people who had at least some interest in taking
an equity position in the dam. 18 would be interested in a long-term water right.
This includes some that were interested in being a part owner of the dam. 10 would
be prepared to take water on an annual basis. There would obviously be difficulties
financing a scheme on this basis."
(Agricultural
and Economic Report, Supplementary DPEMP, June 2002, page 11)
There
is a real risk that, if approved, this project would fail financially, leaving
State and Commonwealth Government’s the options of either writing off their input
or pumping even more public money into the dam. Creating a situation where this
is a possibility is not good public policy.
In
summary, there are serious problems with the financial viability of this proposal,
and many factors that must be re-assessed.
6.
On-farm storage option
The document entitled Development
Report: Assessment of On-Farm Storages as an alternative to the Meander Dam
provides a limited desk top analysis of the potential for further farm dams in
the Meander Valley. The TCT is deeply concerned about the number of errors and
flawed assumptions within this document, and we note that ACIL Tasman has also
expressed concerns about its conclusions. This report seems to ignore the following
benefits that on-farm storage provides:
-
the
increase in the capital value of a property that an on-farm dam brings;
-
the
likelihood of landholders borrowing money to build on-farm dams and therefore
not having any up-front costs; and
-
the
tax benefits associated with construction of on-farm infrastructure, particularly
with regards to loans.
ACIL
Tasman made the following comments in the document Third Report: review of
Marsden Jacob Associates report (June 2003)
"We
have reservations about two of the main assumptions in the National Strategic
Services analysis in particular.
- One
is the assumption, said to be derived from a Davey & Maynard demand study
that irrigators could not afford to spend more than $55/ML. In fact the surplus
available to farmers, and thus their willingness to pay for irrigation water,
especially for poppies and potatoes and other vegetables, appears to be a great
deal higher than $55/ML.
- MJA
are aware that the $55 assumption is misleading - their own report criticises
another (one for the TCT written by Edwards in December 2002) for making an assumption
that farmers could afford as little as $75/ML!. (eg, see Exec Summ, p iv).
- The other is the assumption,
related to the above, that the most suitable sites for farm dams are prohibitively
distant from the areas suitable for irrigated agriculture.
- By contrast, during our
visit to Tasmania in May, we gained the impression that the areas best suited
for irrigated crops are some distance from the River and quite close to good dam
sites.
ACIL
Tasman’s view, therefore, is that the National Strategic Services assessment of
the viability of farm dams is suspect. Presumably the final MJA Economic Analysis
will contain a more searching analysis of this issue. It seems unlikely that the
facts of the matter will threaten MJA’s conclusion that the Meander Dam Project
is viable, but some reduction of the assessed Dam Project benefits relative to
the Without Project case may be necessary." (page 6)
We
note that this readjustment has not occurred.
Flawed
as this document is, it still comes to the conclusion that:
"…it is estimated that
the potential identified yield from new dams would range between 7,354 ML in the
most optimistic scenario to 4,295 Ml in the most likely scenario." (page
46)
Thus,
there would appear to be absolutely no question that there is still sufficient
on-farm storage sites left in the Meander Valley to more than compensate for any
new environmental flow regime that might be implemented in the Meander River in
the near future. This in reinforced by the fact that since September 2001, on-farm
dams with a total capacity of around 2,000 ML have been formally applied for in
the Meander Valley. This is an important point, as one of the two major justifications
for this proposal is to avoid loss of farm revenue due to the implementation of
environmental flows.
The
other main justification for this project is the Tasmanian Government’s stated
intent to double agricultural production by 2008. There has never been any investigation
as to whether or not this policy is sustainable or even achievable, or how it
can be reconciled with Tasmania’s commitment to water reform.
This
raises a key question - of whether or not the Commonwealth should support ill-conceived,
unsustainable State Government policies and proposals. There is no question that
landholders in the Meander Valley should be assisted in dealing with water reform
initiatives such as environmental flows, and it is entirely acceptable to allocate
public funding to achieve this. However, there is no justification for the Commonwealth
supporting the expensive, unsustainable expansion of agriculture in an already
stressed catchment, particularly when the same argument could be applied to any
number of catchments Australia-wide.
7.
Social and community impacts of the proposal
The
document entitled Meander Dam: Social and Community Impacts has been prepared
to justify the social benefit of the proposed dam. The relevance of this report
is problematic given that it simply accepts the underlying premises and assumptions
attached to the proponent's economic case for the dam and ignores the findings
of the Tasmanian RMPAT appeal. This is a position that at the very least needs
to be re-visited in the Commonwealth response. Where is the critical analysis
of the socio-economic impact contained in the proponents original 'rationale'?
The
social capital issues identified in this document are real but they are systemic
of regional and rural decline not enhanced or undermined by the existence or otherwise
of the dam proposal. The obvious strategy would be to transfer the net public
subsidy attached to the dam into substantive policy responses to the established
social capital issues outlined in the report - such as VET and farm management
training programs such as RITE.
The
most disturbing aspect of using this report at this time in the process is that
even when it uncritically accepts the assumptions and premises of the proponent's
case it is unable to provide anything other than an entirely ambiguous level of
support. The report is riddled with statements such as: 'likely to have' ; 'there
is likely'; 'may increase'; 'there may be more'. It is not unreasonable to assume
that this is language from an academic perspective that remains unconvinced of
the case advanced.
The
ambiguity of this document is reinforced by the final point made under ‘Conclusions’
on page 5:
"Economic,
social and community outcomes would be enhanced through a broad program of education
and training, including farmer learning groups in which farmers are active leaders,
social and educational skills development and development of community and agricultural
sector structures that reach out to external knowledge resources."
Whilst
relevant and important, this has absolutely nothing whatsoever to do with the
proposed Meander Dam.
There
is no question that the Meander Valley is a vulnerable rural community and that
it should be a priority area for assistance. However, key issues which should
be addressed in any such assistance package, such as increased education and training,
are entirely independent of any specific project, including the proposed Meander
Dam.
8.
Unresolved issues
There are still a number unresolved
issues with regards to the ecological sustainability and operational (and therefore
financial and economic) viability of this proposal. The proponent has chosen to
selectively ignore these issues, which have the potential to impact upon the viability
of this proposal.
Land capability and
salinity
The
capability of the land to handle increased irrigation in relation to the areas
of highest demand has not been addressed. Nor has the localised impacts of salinity
and water logging on productivity been examined. In the original DPEMP there is
a serious error in the differentiation within the Class 4 land category. This
is done even though it is conceded such divisions may not be readily distinguishable.
One possible conclusion for this, given the overall positive bias within this
document, is to improve the perceived viability of the proposal. It is quite possible
that the majority of Class 3 land (most suitable for irrigation) in the area may
already be under irrigation, seriously weakening the need for the proposed dam
or any resultant increase in productivity.
Until
a proper assessment of demand related to land capability and cross-referenced
with areas with potential salinity and/or water logging problems, serious questions
must be raised about the potential to sustainably increase productivity in this
area.
The
issue of sediment build up within the dam is a real one, and has not been addressed
by the proponent. The area upstream of the dam has been referred to as the most
degraded sub-alpine region in Australia, and large landslips are common. In the
Supplementary DPEMP, Mineral Resources Tasmania make the following comment:
"In
order to thoroughly assess the landslide risk from the impoundment and to the
dam site itself it is recommended that a more detailed engineering geological
investigation of the catchment and planned dam site should be carried out. The
presence of landslides within the storage area and within the catchment has been
acknowledged in the DPEMP but not supported with land stability maps.
Because
of the potential instability of the Western Tiers the frequency, number and types
of landslides and their levels of activity should be established to allow an estimate
to be made of possible quantities of sediments that may been deposited in the
proposed dam. The study should also address the issue of raised groundwater levels
in the catchment as a result of the proposed dam and its potential to increase
the frequency of landslides." (page 21)
In
response, the proponent has commented on the potential for landslips to impact
on the integrity of the dam. In other words, this issue has been completely ignored.
Build up of large amounts of sediment within the dam will ultimately effect its
storage capacity and operation. This in turn will have ramifications of its financial
and economic viability.
Erosion of farmland
downstream
The
issue of increased erosion downstream of the dam, and the subsequent loss of private
property is still unresolved. The document Downstream Meander Dam Fluvial Geomorphology
Assessment (Locher et al, May 2002) found that there would be channel widening
and deepening as well as the high risk of floodplain stripping in three separate
reaches of the Meander River, totaling 11 kilometres. Compensation for landholders
who may lose land has not been factored into any of the proponent’s costings.
9.
National Competition Policy
National Competition
Policy clearly states that:
"Governments
have agreed that all investments in new rural water schemes or extensions to existing
schemes should only be undertaken after appraisal indicates that it is economically
viable and ecologically sustainable." (clause 3d(iii))
The
National Competition Council also have clearly stated the position on water infrastructure
development:
"…
in the past regional development has been used to justify projects that have not
been able to recover their direct costs with proponents arguing that as these
broader gains represent a public benefit the government should cover the shortfall
in the project’s commercial returns. The Council suggests that where broader regional
benefits (such as increased economic activity and employment) are included in
the analysis they should be estimated through a robust and transparent
methodology. Further, these regional benefits need to be compared with their
associated costs. For example, the transaction costs and opportunity cost of the
government providing financial assistance to the project should be considered."
(New
investment in rural water infrastructure NCC, page 3)
No
opportunity costing of $9.6 million of taxpayers money, invested at no return,
has been made for the proposed Meander Dam. With regards to impacts on threatened
species, NCC states the following:
"In
any case, irrespective of the magnitude of the scale of the infrastructure, where
such fauna are considered to be rare, endangered, vulnerable or threatened the
requirement to maintain biodiversity would necessitate due consideration being
given to measures for ensuring the ongoing survival of the species."
(New
investment in rural water infrastructure NCC, page 5)
As
has already been discussed, the building of this dam will dramatically increase
the probability of the extinction of at least one threatened species.
The
NCC also clearly states its position on assessments:
"When
States and Territories assess the ecological sustainability of medium to large
scale infrastructure developments the Council will look to see that appropriate
regulatory and policy structures and decision processes are in place. The Council
will also look for evidence, where available, that these mechanisms are leading
to outcomes consistent with CoAG commitments.
With
regard to this scale of development approvals, the Council would seek assurances
that the process used involves a level of independence and transparency among
parties involved in the process. At the operational level this should equate to
independence among government development agencies, development proponents, individuals
responsible for conducting impact assessments, and government agencies involved
in making recommendations that lead to a decision to proceed or not to proceed
with development."
(New
investment in rural water infrastructure NCC, pages 5 and 6)
This
is an important point. A major and ongoing problem in Tasmania is DPIWE acting
as both proponent and assessing body. In the case of the Meander Dam, the proponent
was the Rivers and Water Supply Commission (RWSC), a Government Business Enterprise
based within DPIWE. The Meander Dam was promoted by the Water Development Branch
(WDB) of DPIWE, which also coordinated the Development Proposal and Environmental
Management Plan. The WDB effectively was the proponent of this proposal, which
was publicly admitted by its manager on a number of occasions. Assessment of the
proposal was conducted by the Environment Division of DPIWE. Internal advice from
within DPIWE is not publicly available, only the Environmental Assessment Report
that was generated by the Environment Division. However, the TCT has obtained
this advice through Freedom of Information, and we will refer to this further
below. The Environmental Assessment Report basically accepted the assertions of
the WDB and recommended approval of this proposal.
The
Assessment report was then passed to the Board of Environmental Management and
Pollution Control for determination. This five member board has amongst its members
the Manager of Environment Division of DPIWE, who effectively generated the report
the board was to consider, the Secretary of DPIWE, who is also the Chair of the
Board. The proposal was subsequently approved.
This
proposal also required approval by the Assessment Committee for Dam Construction
(ACDC). Amongst the 6 person membership of the ACDC is the Manager of Environment
Division of DPIWE, the Manger of the Water Resources Division of DPIWE, and the
Chair of the RWSC. The proposal was subsequently approved.
In
short, the TCT is of the opinion that the assessment and approval of this proposal
was completely compromised by its internal passage through DPIWE and the presence
of individuals with major conflicts of interest on the supposedly independent
approval committees. There is no question that the Minister responsible for DPIWE
had a major political interest in the approval of the dam, and the success of
the TCT’s subsequent appeal underlines our concerns on this issue.
The
use of enabling legislation to over ride Tasmania’s Resource Management and Planning
System to obtain a permit for this proposal also highlights the problems with
assessment and approvals in situations where DPIWE acts as proponent, assessor
and approving body.
NCC
provides further information on the assessment and approval process in this same
document:
"Given
jurisdictions are required to conduct an environmental impact assessment, environmental
management plans or similar approaches the Council will assess; the assessment
process, the decision process, and consequent implementation and subsequent monitoring
to ensure ecological sustainability. In particular, the Council will be looking
for information on:
Decision
process – Where a decision is made to proceed with development following an
impact assessment that indicates an environmental impact will occur, the Council
seeks information on who has decided the level of impact is considered to be ecologically
sustainable, and what considerations were taken into account in forming such a
decision. The reasons for these decisions should be publicly available."
(New
investment in rural water infrastructure NCC, page 6)
The
proposed Meander Dam is without any doubt ecologically unsustainable. This view
was expressed by the General Manager of the Resource Management and Conservation
Division of DPIWE over a year ago in documents obtained under Freedom of Information.
When commenting on the impacts on the Epacris aff. exserta (Union
Bridge) population in an internal email, it is stated that these impacts would
be:
"contrary
to the [Tasmanian] Government’s stated policy position in relation to biodiversity
conservation and constitute environmental harm which is inconsistent with the
objectives of Sustainable Development"
(Attachment
2. Please note that the mapping of substrate referred to in this attachment revealed
that 80% of the population in question was found on erodible substrate and would
therefore be lost.)
(Attachment
3)
(Attachment
4)
Please
also see the original version of the document Impacts of the proposed Meander
Dam on Epacris aff. exserta ‘Union Bridge’ and note that it is annotated
"Water Development Branch put a watered down version of this document in
the DPEMP as appendix 7" (Attachment 5).
There
would appear to be no question that there have been serious problems with the
Tasmanian Government’s internal assessment and approval processes, and that internal
advice contrary to the desired outcome was ignored.
10.
Addressing environmental issues brought to light by the proposal
Many
of the measures that the proponent has suggested to mitigate environmental impacts
can, should, and in some cases are being addressed through other channels. For
example, the TCT recently submitted an Envirofund application to deal with the
issue of human induced mortality in quolls as a result of raids on poultry houses.
This proposal was fully supported by the Nature Conservation Branch, DPIWE, and
demonstrates how these issues can be dealt with. Another example of a conservation
issue that could be dealt with through programs such as Envirofund is weed control
and fencing of populations of Epacris aff. exserta (Union Bridge)
on the Meander River. Conservation covenants and grants could also help protect
those Epacris aff. exserta (Union Bridge) populations that are on
private land, whilst the management arrangements proposed for population within
State Forest can and should proceed independently of the dam.
In
short, this proposal has brought to light a number of environmental issues which
can be addressed through other avenues for a net environmental gain. Should the
dam proceed however, these gains would be quickly countered by significant environmental
damage.
11.
Conclusion
There remain significant, unresolved
issues with this proposal. Importantly, the situation with regards to the major
impacts on Epacris aff. exserta (Union Bridge) has not changed since
the TCT appeal to RMPAT in January of this year. If anything, the outlook for
this species is even bleaker.
In
summary:
-
This
proposal is not ecologically sustainable.
-
Minor
changes to the proposed economic model result in the proposal making an economic
loss.
-
There
are major problems with the financial viability of this proposal, and on a stand
alone basis it is not viable.
-
Although
deeply flawed, the on-farm storage study has revealed that there are still sufficient
options to more than compensate for any increased environmental flow regime in
the Meander River.